As we were finishing up outfitting the boat, we were also working through commissioning – verifying that all the boat’s systems were working as intended. It was a lot to work through, but if I had it to do over, I’d have worked even harder. It’s much easier to resolve any potential warranty issues at the handover stage rather than later. For example, it was only later we noticed a small leak in the heat exchange pipe for the heater. Catching all these potential problems involves a lot of crawling around the boat, opening access panels and peering with a flash light, etc.
Even when an issue is uncovered, getting it resolved is no easy task. We couldn’t talk to Fountaine Pajot directly, we had to report issues to our dealer who reported them to FP who then worked with their contractors (Gulfstream, Uchimata and Pochan) to fix the problem. Many boat buyers hire a local agent who is familiar with the different parties, but we didn’t go that route, so it was a bit hard. Getting all the issues sorted out took much longer than we could have imagined. We were in La Rochelle from Feb 13 to March 27, 2023. Six weeks from when we first stepped on the boat till we sailed away from La Rochelle (we had expected a week or two originally).
Beyond the boat issues we also needed to finalize our US Coast Guard documentation, MMSI number, title, insurance, etc.
In addition to dealing with FP, we also had to work with Pochan (the installers of the Integrel system) to resolve any problems with that system. Sometime there’s a fuzzy line of which party is responsible (e.g. MPPT controls for the 48v battery) in which there is a lot of “it’s that other guys problem”.
The problems we found with the boat were not critical, just minor things (though you’d definitely hope to have them resolved before the handover). This is the list of issues we uncovered:
- Missing cabinet door in master cabin
- Counter to left of sink needs to be buffed out
- Gelcoat chip by life raft locker
- Leg on lounge deck railing is not connected to deck
- Compass is broken
- Depth sounder not installed
- Scratch on starboard side saloon window
- Stanchion for helm roof is leaking
- Integrel system needs to be reconfigured to use solar panels to charge 48v bank and SOC monitor
- We ordered the Miele 7440 Oven with combined microwave but got the Miele 2760 bp electric (no microwave)
- Missing lid for trash receptacle (didn’t know this was a thing till I saw our neighbor’s Tanna)
- Fans installed in heads rather than saloon (this took months to address)
- Missing smoke detector in saloon
- Leak in port rudder
- Leak in the hydraulic steering system
- One of the panels in the master closet is missing two screws
Eventually almost all of these got dealt with. The leak in the hydraulic steering system was only discovered the day we left La Rochelle and it got fixed in Falmouth. Never did get the missing screws for the closet panel!
Our dealer from Seattle flew over and spent a week with us helping with the checkout and dealing with FP. Beyond the commissioning and outfitting efforts we also had three training sessions with our French coaches: Jean and Thomas. Notwithstanding some language barriers, they walked us through the different boat systems and we took out the boat three times for practice sails. Topics covered were: docking, autopilot use, raising/lowering the sails, reefing, anchoring, emergency tiller use – it was a lot to take in over six hours. Even though we had plenty of experience in our 40 ft monohull, the Tanna was a different matter. For example, when docking you could leave the helm alone and just use the port vs starboard engines to maneuver (like driving a tank). Still the size, momentum, and sight lines left you feeling a little like moving a tennis court around the harbour. This was actually the only time we left the dock - we didn’t have an assigned berth, so if we left on our own there was a chance we wouldn’t have a spot to come back to! So other than these training sessions, we’d have to be practicing these skills out in the open ocean.
Anyway, it was a busy six weeks, but finally it was time to cast off. Our plan for the first season was to head north to England and then travel deep into the Baltic Sea. Pretty ambitious for two catamaran newbies! Check out Season1 to learn how we fared.
Voila! Et là, tout fonctionne tout simplement Our fans got installed in the wrong place! Boat deep dive Anchor chain and swivel - the anchor bay was never this clean again! The water pump is a critical piece of equipment In addition to sailing instruction, Thomas installed these shields for the fender lines Folding prop with anodes - later we installed rope cutters Underwater lights which at best cast a dim glow Grounding plate - disperses stray current to water Underwater hatch for access once your boat is capsized! Ramp where you could careen the boat at low tide Watermaker intake On the ramp Our first ding - knocked the transom coming off the ramp A party with fellow boat buyers Checking output of MPPTs - what’s up with MPPT-290? 220v breaker box Going up the mast Installing fender line protectors FP loves silkaflex Leak in stanchion backing plate Ground level view of the mast head Some of the many, many fuses Took advantage of a windless sunset to practice raising the sail Yet another trip to the ramp Investigating a leak in the rudder Running a messenger line to route the starlink cable through the traveler Leak in steering hydraulics - would not want to run out underway! Hydraulic fluid reservoir - I kept a close eye on this until the leak was fixed La Rochelle marina had a lot of boats Going through the handover documents First time taking the boat out! We are sailing! Good sail shape Dinner with our broker at a French restaurant Everyone had a chance to practice Now try backing… Preparing to head out Steering through the marina